Town of Central Butte Water Treatment Plant Upgrade
Federal contribution
$390,000
Federal share40%
of $975.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2021
202120222023202420252026
BuiltForecast
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Central Butte
- Construction start
- May 9, 2023(actual)
- Construction end
- Feb 13, 2026(forecast)
Also in Central Butte