Water Well Upgrade
Federal contribution
$50,140
Federal share50%
of $100.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
2017
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Central Butte
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Nov 9, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end17 months earlyforecast Mar 31, 2019