Town of Esterhazy Regional Water System
Federal contribution
$12.0M
$11,970,000
Federal share40%
of $29.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2021
today
2021202320252027
BuiltForecast
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Esterhazy
- Construction start
- May 1, 2022(actual)
- Construction end
- Dec 31, 2026(forecast)