Sewer Force Main Upgrades
Federal contribution
$840,000
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 11, 2017
201720182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Esterhazy
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Mar 7, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end3 weeks earlyforecast Mar 31, 2019
Also in Esterhazy
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48454 in the federal list. How to read these figures.