2020/2021 Electric School Buses

Charlottetown, Prince Edward Island

completeGreen EnergyGIS
Federal contribution
$2.1M
$2,100,000
Federal share50%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 9, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 31, 2020(actual)
Construction end
Mar 5, 2021(actual)

Against the original forecast

  • Construction end2 months lateforecast Dec 31, 2020