Upgrading/Relocation of Wastewater Lagoon

Matachewan First Nation, Ontario

underwayWastewaterGIS
Federal contribution
$309,375
Federal share75%

of $412.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
today
202120222023202420252026
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Matachewan First Nation
Construction start
Oct 17, 2024(actual)
Construction end
Sep 30, 2026(forecast)

Against the original forecast

  • Construction start5 months lateforecast May 10, 2024