Matachewan First nation water treatment plant equipment upgrade and replacement

Matachewan First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$44,616
Federal share43%

of $103.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Matachewan First Nation
Construction start
Feb 1, 2017(actual)
Construction end
Jan 4, 2018(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2018

Also in Matachewan First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50332 in the federal list. How to read these figures.