Mary Street Water, Wastewater and Storm Sewer Replacement
South Bruce Peninsula, Ontario
Federal contribution
$1.1M
$1,099,008
Federal share40%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2021
202120222023
Built
Approved 8 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Corporation of the Town of South Bruce Peninsula
- Construction start
- May 2, 2022(actual)
- Construction end
- Sep 29, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 4, 2022
- Construction end2 months earlyforecast Nov 30, 2023
Also in South Bruce Peninsula
- Gould Street and Pengally Avenue Watermain Replacement$1.1M
- Design Upgrades for Sewage Pump Station #1 located at 524 Taylor Street, Wiarton$85.0K
- Bluewater Park Trail Enhancement$80.0K
- Gravity Sewer Inflow and Infiltration Investigation in Wiarton - work will occur throughout Wiarton, but will concentrate on Berford Street between Frank Street and Division Street$78.7K
- Albemarle Brook Restoration: Fresh water sustainability for Sky Lake, the Rankin River system and recreation at Sauble beach$45.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57287 in the federal list. How to read these figures.