Albemarle Brook Restoration: Fresh water sustainability for Sky Lake, the Rankin River system and recreation at Sauble beach

South Bruce Peninsula, Ontario

approvedOtherNIF
Federal contribution
$45,840
Federal share80%

of $57.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2026
today
20252026
BuiltForecast

Approved 18 months before the announcement.

Program
Natural Infrastructure Fund
Construction start
Jul 1, 2026(forecast)
Construction end
Oct 31, 2026(forecast)

Also in South Bruce Peninsula

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66100 in the federal list. How to read these figures.