Bus Shelters (Phase 2)
Federal contribution
$8.0M
$7,973,683
Federal share40%
of $19.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2021
today
20212023202520272029
BuiltForecast
Approved 6 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- British Columbia Transit
- Construction start
- Oct 1, 2020(actual)
- Construction end
- Mar 1, 2029(forecast)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2020
Also in Undefined