Back to projects

Couchiching First Nation Stormwater Management Infrastructure Upgrades

Couchiching First Nation, Ontario

approvedWastewaterGIS
Federal contribution
$2.2M
$2,191,548
Federal share75%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
202120222023202420252026
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Couchiching First Nation
Construction start
Jun 1, 2025(forecast)
Construction end
Oct 31, 2025(forecast)

Also in Couchiching First Nation