Water and Wastewater Servicing Feasibility Study – Assessment of Feasibility of Community Standalone System

Couchiching First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$80,786
Federal share50%

of $161.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Couchiching First Nation
Construction start
Jan 15, 2018(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start9 months lateforecast Apr 1, 2017

Also in Couchiching First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51425 in the federal list. How to read these figures.