Back to projects

Lift Station Upgrade

Steady Brook, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$90,683
Federal share40%

of $226.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2021
20212022
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Steady Brook
Construction start
Jul 1, 2022(actual)
Construction end
Oct 7, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 15, 2022
  • Construction end5 months earlyforecast Feb 28, 2023

Also in Steady Brook