Sagamok Anishnawbek Water Infrastructure

Sagamok Anishnawbek First Nation, Ontario

underwayDrinking WaterGIS
Federal contribution
$2.2M
$2,183,063
Federal share75%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
today
2021202320252027
BuiltForecast

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Aug 2, 2021(actual)
Construction end
Oct 31, 2026(forecast)

Also in Sagamok Anishnawbek First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57307 in the federal list. How to read these figures.