Proposed Subdivision - New Water main
Sagamok Anishnawbek First Nation, Ontario
Federal contribution
$74,631
Federal share30%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Sagamok Anishnawbek First Nation
- Construction start
- Jun 15, 2018(actual)
- Construction end
- Dec 18, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 3, 2018
- Construction end5 months lateforecast Aug 3, 2018
Also in Sagamok Anishnawbek First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52454 in the federal list. How to read these figures.