Rural Municipality of Swift Current No. 137, Unvoas Bridge Replacement
Swift Current No. 137, Saskatchewan
Federal contribution
$124,988
Federal share17%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 11, 2021
2021
Built
Approved 8 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Swift Current No. 137
- Construction start
- Sep 1, 2021(actual)
- Construction end
- Nov 5, 2021(actual)
Against the original forecast
- Construction start11 months lateforecast Oct 1, 2020
- Construction end8 weeks earlyforecast Dec 31, 2021