Rural Municipality (RM) of Swift Current No. 137, Grid 630 Bridge Replacement

Swift Current No. 137, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$166,650
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2021
2021
Built

Approved 9 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 20, 2021(actual)
Construction end
Nov 5, 2021(actual)

Against the original forecast

  • Construction start9 months lateforecast Jan 1, 2021

Also in Swift Current No. 137

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57341 in the federal list. How to read these figures.