Town of Pense Arena Flooring and Piping Upgrades
Federal contribution
$342,440
Federal share40%
of $856.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
20212022
Built
Approved 6 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Pense
- Construction start
- Apr 1, 2022(actual)
- Construction end
- Sep 30, 2022(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2022
Also in Pense
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57378 in the federal list. How to read these figures.