Town of Pense - Wastewater Infrastructure Upgrades

Pense, Saskatchewan

completeWastewaterGIS
Federal contribution
$368,160
Federal share40%

of $920.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 29, 2024
202420252026
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Pense
Construction start
Mar 1, 2025(actual)
Construction end
Dec 17, 2025(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2026