Pic River Water Treatment Plant Replacement
Biigtigong Nishnaabeg (Ojibways of the Pic River First Nation), Ontario
Federal contribution
$2.2M
$2,223,360
Federal share75%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 15, 2020
202120222023202420252026
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Biigtigong Nishnaabeg
- Construction start
- Apr 16, 2024(actual)
- Construction end
- Dec 31, 2025(forecast)
Against the original forecast
- Construction start15 months lateforecast Jan 1, 2023
Also in Biigtigong Nishnaabeg (Ojibways of the Pic River First Nation)