Source Water Capacity Investigation
Biigtigong Nishnaabeg (Ojibways of the Pic River First Nation), Ontario
Federal contribution
$59,244
Federal share50%
of $118.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 3 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Biigtigong Nishnaabeg
- Construction start
- Jan 15, 2018(actual)
- Construction end
- Jun 30, 2019(actual)
Against the original forecast
- Construction start11 months lateforecast Feb 1, 2017
- Construction end16 months lateforecast Mar 1, 2018
Also in Biigtigong Nishnaabeg (Ojibways of the Pic River First Nation)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50380 in the federal list. How to read these figures.