Anishinaabeg of Naongashiing Sewage Lagoon

Anishinaabeg of Naongashiing, Ontario

underwayWastewaterGIS
Federal contribution
$2.2M
$2,240,235
Federal share26%

of $8.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
20212022202320242025
BuiltForecast

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 15, 2024(actual)
Construction end
Oct 16, 2025(forecast)

Against the original forecast

  • Construction start17 months lateforecast Apr 17, 2023

Also in Anishinaabeg of Naongashiing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57392 in the federal list. How to read these figures.