Equipment Upgrades at Sewage Pumping Station

Anishinaabeg of Naongashiing, Ontario

completeWastewaterCWWF
Federal contribution
$88
Federal share3%

of $3.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
20182019202020212022
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Apr 1, 2019(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction start2.2 years lateforecast Feb 1, 2017
  • Construction end3 months lateforecast Mar 30, 2022