Fare Collection System Upgrade
St. John's, Newfoundland and Labrador
Federal contribution
$169,638
Federal share45%
of $379.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of St. John's
- Construction start
- Nov 30, 2020(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jan 1, 2021
- Construction end4 weeks earlyforecast Jul 31, 2022
Also in St. John's