Back to projects

Fare Collection System Upgrade

St. John's, Newfoundland and Labrador

completePublic TransitPTIS
Federal contribution
$169,638
Federal share45%

of $379.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20212022
Built

Approved 7 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of St. John's
Construction start
Nov 30, 2020(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jan 1, 2021
  • Construction end4 weeks earlyforecast Jul 31, 2022

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57408 in the federal list. How to read these figures.