City of Saskatoon Utility Scale Solar Power Plant
Federal contribution
$1.4M
$1,400,000
Federal share40%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
today
20222023202420252026
BuiltForecast
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Saskatoon
- Construction start
- Jun 16, 2025(actual)
- Construction end
- Aug 31, 2026(forecast)
Also in Saskatoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57447 in the federal list. How to read these figures.