City of Saskatoon Spadina Lift Station

Saskatoon, Saskatchewan

completeWastewaterGIS
Federal contribution
$7.2M
$7,200,000
Federal share40%

of $18.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022202320242025
Built
Program
Green Infrastructure Stream
Ultimate recipient
City of Saskatoon
Construction start
Sep 22, 2021(actual)
Construction end
Mar 25, 2025(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jan 3, 2022
  • Construction end5 months lateforecast Nov 1, 2024