Gull Bay Lagoon Expansion

Kiashke Zaaging Anishinaabek (Gull Bay First Nation), Ontario

completeWastewaterGIS
Federal contribution
$2.2M
$2,218,545
Federal share75%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
20212022202320242025
Built

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Gull Bay First Nation
Construction start
Dec 1, 2023(actual)
Construction end
Sep 7, 2025(actual)

Against the original forecast

  • Construction start7 months earlyforecast Jul 1, 2024
  • Construction end8 weeks earlyforecast Oct 31, 2025

Also in Kiashke Zaaging Anishinaabek (Gull Bay First Nation)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57532 in the federal list. How to read these figures.