Wastewater Planning Study and Detailed Design, and Flow meter purchase
Kiashke Zaaging Anishinaabek (Gull Bay First Nation), Ontario
Federal contribution
$49,998
Federal share38%
of $131.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2021
20182019202020212022
Built
Approved 3.4 years before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Gull Bay First Nation
- Construction start
- Aug 5, 2019(actual)
- Construction end
- Jun 10, 2022(actual)
Against the original forecast
- Construction start20 months lateforecast Dec 1, 2017
- Construction end16 months earlyforecast Sep 30, 2023
Also in Kiashke Zaaging Anishinaabek (Gull Bay First Nation)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51956 in the federal list. How to read these figures.