Wastewater Planning Study and Detailed Design, and Flow meter purchase

Kiashke Zaaging Anishinaabek (Gull Bay First Nation), Ontario

completeWastewaterCWWF
Federal contribution
$49,998
Federal share38%

of $131.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
20182019202020212022
Built

Approved 3.4 years before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Gull Bay First Nation
Construction start
Aug 5, 2019(actual)
Construction end
Jun 10, 2022(actual)

Against the original forecast

  • Construction start20 months lateforecast Dec 1, 2017
  • Construction end16 months earlyforecast Sep 30, 2023