Moose Cree Sewage System Rehabilitation

Moose Cree First Nation, Ontario

completeWastewaterGIS
Federal contribution
$2.1M
$2,142,743
Federal share75%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2021
2022
Built

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Moose Cree First Nation
Construction start
Jan 31, 2022(actual)
Construction end
May 31, 2022(actual)

Against the original forecast

  • Construction start3 months lateforecast Nov 4, 2021
  • Construction end11 months earlyforecast Apr 21, 2023

Also in Moose Cree First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57536 in the federal list. How to read these figures.