Moose Factory Sewage Lagoon Upgrade

Moose Cree First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$128,000
Federal share50%

of $256.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
2018
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Moose Cree First Nation
Construction start
Nov 15, 2017(actual)
Construction end
Jun 28, 2018(actual)

Against the original forecast

  • Construction start12 months lateforecast Nov 1, 2016
  • Construction end4 weeks lateforecast May 30, 2018

Also in Moose Cree First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51377 in the federal list. How to read these figures.