Renovation and renewal of the elevators at the Fitness and Recreation centres in the YMCA Of Northeastern Ontario

Greater Sudbury, Ontario

underwayRecreationCCRIS
Federal contribution
$277,935
Federal share40%

of $694.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
today
2021202320252027
BuiltForecast

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
YMCA of Sudbury
Construction start
Oct 1, 2023(actual)
Construction end
Mar 31, 2027(forecast)

Against the original forecast

  • Construction start12 months lateforecast Sep 26, 2022

Also in Greater Sudbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57558 in the federal list. How to read these figures.