Renovation of the kitchen in the community centre at 36 Main Street in Penetanguishene
Federal contribution
$26,461
Federal share40%
of $66.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 8, 2021
20212022
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- La Clé
- Construction start
- May 1, 2021(actual)
- Construction end
- Jan 14, 2022(actual)
Against the original forecast
- Construction start2 months earlyforecast Jul 1, 2021
- Construction end2 weeks earlyforecast Jan 31, 2022
Also in Penetanguishene