Back to projects

Seating replacement

Kitchener, Ontario

completeRecreationCCRIS
Federal contribution
$540,000
Federal share40%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2021
2021202220232024
Built

Approved 6 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Centre In The Square
Construction start
Jul 4, 2023(actual)
Construction end
Sep 13, 2024(actual)

Also in Kitchener