Replacing Synthetic Soccer Field Surface at Sainte-Famille Park
Federal contribution
$172,401
Federal share33%
of $522.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 6, 2021
2021202220232024
BuiltForecast
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Québec
- Construction start
- Oct 5, 2023(forecast)
- Construction end
- Jul 31, 2024(forecast)
Also in Québec