Construction of a Baseball Field - Saint-Colomban
Federal contribution
$147,573
Federal share33%
of $446.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2021
202120222023
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Saint-Colomban
- Construction start
- Aug 18, 2022(actual)
- Construction end
- May 29, 2023(actual)
Also in Saint-Colomban