Back to projects

Construction of a Baseball Field - Saint-Colomban

Saint-Colomban, Quebec

completeRecreationCCRIS
Federal contribution
$147,573
Federal share33%

of $446.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 18, 2021
202120222023
Built

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Saint-Colomban
Construction start
Aug 18, 2022(actual)
Construction end
May 29, 2023(actual)

Also in Saint-Colomban

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57656 in the federal list. How to read these figures.