New library construction
Federal contribution
$1.1M
$1,100,400
Federal share35%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 20, 2022
today
20232024202520262027
BuiltForecast
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Saint-Colomban
- Construction start
- Sep 1, 2025(actual)
- Construction end
- Nov 15, 2026(forecast)
Also in Saint-Colomban
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64947 in the federal list. How to read these figures.