Back to projects

Universal Access in Facility to Enhance Cultural Programming

Toronto, Ontario

completeCultureCCRIS
Federal contribution
$294,800
Federal share40%

of $737.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20212022202320242025
Built

Approved 7 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Feb 16, 2021(actual)
Construction end
Nov 29, 2024(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Oct 31, 2024

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57695 in the federal list. How to read these figures.