Construction of Youth Hub - South Fletchers
Federal contribution
$565,000
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2021
2021202220232024
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Corporation of the City of Brampton
- Construction start
- Jul 13, 2022(actual)
- Construction end
- Apr 24, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 2, 2022
- Construction end16 months lateforecast Dec 30, 2022
Also in Brampton
- Transit Maintenance & Storage Facility$69.9M
- Protecting our future: Flood mitigation and physical, economic, social and cultural resilience for historic downtown Brampton, on by reconstructing 600M of the concrete Etobicoke Creek bypass channel$38.9M
- 2023 Replacement Buses$25.5M
- 2020-2024 Bus Refurbishments$22.2M
- 2020 Growth Buses$18.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57716 in the federal list. How to read these figures.