Construction of Youth Hub - South Fletchers

Brampton, Ontario

completeRecreationCCRIS
Federal contribution
$565,000
Federal share40%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2021
2021202220232024
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Jul 13, 2022(actual)
Construction end
Apr 24, 2024(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 2, 2022
  • Construction end16 months lateforecast Dec 30, 2022

Also in Brampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57716 in the federal list. How to read these figures.