Modernization of Washroom and Change Room for Fitness Centre at Seniors' Centre
Federal contribution
$66,525
Federal share40%
of $166.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 9, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- North York Seniors Centre (NYSC)
- Construction start
- Sep 3, 2021(actual)
- Construction end
- Feb 15, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 2, 2021
- Construction end18 months lateforecast Aug 31, 2021
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57726 in the federal list. How to read these figures.