Sandwich Teen Action Group Roof Revitalization
Federal contribution
$29,560
Federal share40%
of $73.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2021
2021
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- The Sandwich Teen Action Group
- Construction start
- Apr 1, 2021(actual)
- Construction end
- May 31, 2021(actual)
Against the original forecast
- Construction end3 months earlyforecast Sep 1, 2021
Also in Windsor