Washroom Replacement

Kitchener, Ontario

completeRecreationCCRIS
Federal contribution
$1.2M
$1,200,000
Federal share40%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2021
202120222023
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Kitchener
Construction start
Jun 27, 2022(actual)
Construction end
Mar 15, 2023(actual)

Against the original forecast

  • Construction end2 months lateforecast Dec 31, 2022