Renovation of a Not-for-Profit Community Hub

Toronto, Ontario

completeCultureCCRIS
Federal contribution
$1.2M
$1,172,655
Federal share40%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
2021202220232024
Built

Approved 7 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Mar 31, 2021(actual)
Construction end
Mar 12, 2024(actual)