Upgrading of the Beaupré woodland
Federal contribution
$75,955
Federal share33%
of $227.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 31, 2021
202120222023
BuiltForecast
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of La Pocatière
- Construction start
- Sep 1, 2022(forecast)
- Construction end
- Aug 16, 2023(forecast)
Also in La Pocatière
- Constructino of a New Arena and Community Hall$4.3M
- Repair of the steps and foundation wall at the main entrance of the CLSC at Notre-Dame-de-Fatima Hospital in La Pocatière$420.6K
- Renovation of a Room Adapted for Clientele with Reduced Mobility$390.7K
- Repair of the floor and mechanical systems of the gymnasium$286.0K
- Reflection of toilet bloc in Block B of the Cégep de La Pocatière$183.6K