Back to projects

Repair of the steps and foundation wall at the main entrance of the CLSC at Notre-Dame-de-Fatima Hospital in La Pocatière

La Pocatière, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$420,553
Federal share80%

of $525.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 9, 2024
2024
Built

Approved 16 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 1, 2023(actual)
Construction end
Nov 15, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 17, 2023
  • Construction end7 weeks earlyforecast Dec 31, 2023

Also in La Pocatière