Insulation of the ceiling and replacement of the heating system of the gymnastics hall

Salaberry-de-Valleyfield, Quebec

completeRecreationCCRIS
Federal contribution
$110,350
Federal share33%

of $331.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2021
20212022
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
May 2, 2022(actual)
Construction end
Nov 16, 2022(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 16, 2022