Enhancing Accessibility and Safety at The Mount Community Centre
Federal contribution
$846,285
Federal share40%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 9, 2021
today
202120222023202420252026
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- The Mount Community Centre
- Construction start
- Apr 1, 2022(actual)
- Construction end
- Aug 28, 2026(forecast)