Norseman Pool Rehabilitation
Federal contribution
$2.0M
$1,983,415
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 6, 2021
202220232024
Built
Approved 7 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Toronto
- Construction start
- Oct 3, 2022(actual)
- Construction end
- Apr 8, 2024(actual)
Against the original forecast
- Construction end5 months lateforecast Nov 17, 2023
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57782 in the federal list. How to read these figures.