Norseman Pool Rehabilitation

Toronto, Ontario

completeRecreationCCRIS
Federal contribution
$2.0M
$1,983,415
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 6, 2021
202220232024
Built

Approved 7 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
City of Toronto
Construction start
Oct 3, 2022(actual)
Construction end
Apr 8, 2024(actual)

Against the original forecast

  • Construction end5 months lateforecast Nov 17, 2023