Moira Lake Trail Bridge
Federal contribution
$397,900
Federal share40%
of $994.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Centre Hastings
- Construction start
- Jul 5, 2021(actual)
- Construction end
- Jul 24, 2022(actual)
Against the original forecast
- Construction end8 weeks lateforecast May 31, 2022