Back to projects

Removal of built-up sludge at the Madoc Wastewater Lagoon to restore design volume of 1008 m3/day

Centre Hastings, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share19%

of $265.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2017
2018
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 1, 2018(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 15, 2017
  • Construction end5 months lateforecast Jun 30, 2018

Also in Centre Hastings

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50287 in the federal list. How to read these figures.