Removal of built-up sludge at the Madoc Wastewater Lagoon to restore design volume of 1008 m3/day
Federal contribution
$50,000
Federal share19%
of $265.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Centre Hastings
- Construction start
- May 1, 2018(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 15, 2017
- Construction end5 months lateforecast Jun 30, 2018
Also in Centre Hastings
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50287 in the federal list. How to read these figures.