Upgrades and Expansions to the Existing Community Centre
Federal contribution
$2.8M
$2,835,883
Federal share40%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2021
today
20212023202520272029
BuiltForecast
Approved 7 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Chinese Cultural Centre of Greater Toronto
- Construction start
- Jul 10, 2021(actual)
- Construction end
- Mar 30, 2030(forecast)
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57935 in the federal list. How to read these figures.